Since 1990, HGC is engaged in acquisition and utilization of landfill gases as well as pollution control and the fermentation of organic waste. In this area HGC operates various customer systems within the scope of service contracts. Based on this experience HGC 2007 planned the first biogas plant with biogas upgrading and feeding into the natural gas grid. Many other plants followed until the amendment of the EEG 2014th.

Besides these activities, a variety of biogas transport systems for the collection of biogas and use in satellite CHP were planned and fulfilled by HGC.

Currently the focus of activities in biogas technology is the optimization, expansion and renovation of existing facilities in the areas of gas detection systems, plant engineering, automation and reliability.

References

BIOGAS UPGRADE AND FEED-IN STATION

Project:
Biogas upgrade and feed-in station, installation of two CHP, mechnaical biological waste tretment, Rostock



Customer:
HanseWerk Natur GmbH / Stadtwerke Rostock AG


Services:
All project phases of HOAI (functional tender), 2008-2011


Additional Information:
Biogas from waste treatment, implementation of a desulphurization plant (H2S values ​​> 2.0000 ppm), amino scrubbing (700 m³ / h raw biogas), two cogeneration plant (625 kW electrical capacity each)


rostock_1 rostock_2 rostock_3

BIOGAS UPGRADE STATION ALTENSTADT

Project:
Biogas upgrade station, Altenstadt

 


Customer:
EAM Energie GmbH


Services:
All project phases of HOAI (functional tender), 2011-2012


Additional Information:
Glycol scrubbing (1.400 Nm³/h raw biogas)


altenstadt_1 altenstadt_2 altenstadt_3

BIOGAS PLANT WEISSENBORN-LÜDERODE

Project:
Biogas plant Weißenborn - Lüderode


Customer:
EW Eichsfeldgas GmbH


Services:
All project phases of HOAI, Europe-wide tender (functional tender), 2010-2013


Info:
Planning of the complete system, consisting of fermentation process, biogas upgrade and feed-in station (900 m³ / h raw biogas); amino scrubbing


weissenborn_1 weissenborn_2 weissenborn_3

DRYER AND COMPRESSOR STATION FOR BIOGAS, SCHUBY

Project:
Dryer and compressor station for biogas, Schuby


Customer:
HanseWerk Natur GmbH


Services:
All project phases of HOAI, 2008-2009


Additional Information:
Planning of the complete system consisting of compressor station, biogas supply and decentral CHP (200 kW electrical capacity)


schuby_1

schuby_2

schuby_3

DRYER AND COMPRESSOR STATION FOR BIOGAS, WITTENBERGE

Project:
Dryer and compressor station for biogas, Wittenberge


Customer:
HanseWerk Natur GmbH


Services:
All project phases of HOAI, planning the compressor station and the biogas supply to the decentral CHP, 2009-2010


Additional Information:
Biogas supply for transporting 400 m³ / h, CHP (840 kW electrical capacity)


wittenberge_1 wittenberge_2 wittenberge_3

LANDFILL GEORGSWERDER

Project:
Landfill Georgswerder


Customer:
FHH - Behörde für Umwelt und Energie Hamburg


Services:
Ongoing operational management of the Landfill gas capture and transport system for 25 years.


Additional Information:
Collecting of 120 m³ / h landfill gas from 40 wells, dehumidification and cleaning of the raw landfill gas by cooling, gas transport for further use in an industrial company


georgswerder_1

georgswerder_2

georgswerder_3